  • On 24th May, 2003, Hon’ble Prime Minister of India launched a scheme, formulated by Central Electricity Authority (CEA), for preparation of Preliminary Feasibility Report (PFRs) of 162 New Hydro Electric Schemes totaling to over 50,000 MW.  All the PFRs were targeted to be completed by September, 2004.
  • CEA was entrusted with the overall responsibility for the scheme.
  • Preparation of PFRs involves conceptual planning, preparation of project and equipment layouts, infrastructure requirement, environmental and geological studies, power evacuation arrangement, cost estimates and economic evaluation.
  • PFRs of all the 162 schemes have been prepared ahead of schedule.  The schemes are located in 16 states as under :

Sl. No.

State

Number of Schemes

Installed Capacity (MW)

1

Andhra Pradesh

1

81

2

Arunachal Pradesh

42

27293

3

Chhattisgarh

5

848

4

Himachal Pradesh

15

3328

5

Jammu & Kashmir

13

2675

6

Karnataka

5

1900

7

Kerala

2

126

8

Madhya Pradesh

3

205

9

Maharashtra

9

411

10

Manipur

3

362

11

Meghalaya

11

931

12

Mizoram

3

1500

13

Nagaland

3

330

14

Orissa

4

1189

15

Sikkim

10

1469

16

Uttaranchal

33

5282

Total

 

162

47930

  •  Preparation of DPRs for Low Tariff Schemes

Sl. No.

Particulars

Number

IC (MW)

1

Total PFRs

162

47930

2

PFRs with Tariff upto Rs. 2.50 per unit

78

34020

3

International Issue/Wild Life/Others

05

1084

4

DPRs to be Prepared

73

32936