Home
Mini Ratna Category-I PSU
 

Search:
Introduction
XI Plan (2007−2012)
Beyond XI Plan 
Beyond XIth Plan
Updated On :- 27/07/2010

S No.ProjectCountry/State Capacity Total Capacity Status
1DibangArunachal Pradesh12 * 2503000Awating clearances
2Kotli Bhel Stage - I BUttarakhand4 * 80320Awating clearances
3Kotli Bhel Stage - IIUttarakhand8 * 66.25530Awating clearances
4Pakal Dul*Jammu & Kashmir4 * 2501000Awating clearances
5Kotli Bhel Stage - I AUttarakhand3 * 65195Awating clearances
6Teesta - IVSikkim4 * 130520Awating clearances
7Kiru*Jammu & Kashmir4 * 150600Awating clearances
8Kwar*Jammu & Kashmir4 * 130520Awating clearances
9Tawang-IArunachal Pradesh3 * 200600Awating clearances
10Loktak Downstream*Manipur 2 * 3366Awating clearances
11Tawang-IIArunachal Pradesh4 * 200800Awating clearances
12Tipaimukh*Manipur 6 * 2501500Awating clearances
13Kishenganga Jammu & Kashmir3 * 110330Under Construction
14BursarJammu & Kashmir4 * 2551020Under Survey and Investigation Stage
15Karmoli Lumti TulliUttarakhand2 * 27.555Under Survey and Investigation Stage
16Garba TawaghatUttarakhand3 * 210630Under Survey and Investigation Stage
17Chungar ChalUttarakhand2 * 120240Under Survey and Investigation Stage
18LachenSikkim3 * 70210Under Survey and Investigation Stage
19Goriganga-IIIAUttarakhand3 * 40120Under Survey and Investigation Stage
20Dhauliganga IntermediateUttarakhand3 * 70210Under Survey and Investigation Stage
   Total12466 

* Under Joint Venture

 

 

Projects under category ‘Under Survey and Investigation Stage’ are for survey & investigation for preparation of PFR/FR/DPR of the project for getting various statutory clearances. For preparation of these reports, various hydrological, geological, meteorological, power potential studies etc are carried out at the project site.

Projects under ‘Awaiting clearances’ category are awaiting various statutory clearances from CWC / CEA / MOP / MOWR/PIB and investment sanction from Cabinet Committee on Economic Affairs (CCEA) after preparation of DPRs.